10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.
The AL-GC exam has 115 questions and runs 5 hours 30 minutes.
These 10 free AL-GC questions are organized by exam domain, so you can see how each part of the Alabama Building Construction (Commercial) General Contractor Trade Exam blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: General Requirements
Question 1
During a morning trench inspection, a superintendent finds an employee preparing to enter a 7-foot-deep excavation in Type C soil. No shield, shoring, or compliant slope is in place, and the nearest ladder would require 40 feet of lateral travel. Which set of conditions must be in place before entry resumes?
Show answer & explanation
Correct answer: C - Install compliant cave-in protection, obtain the competent-person inspection, and provide safe egress within 25 feet before anyone enters
Question 2
A new accessible ramp segment has a 1:13 running slope, a 5.5-inch total rise, 36 inches of clear width, and 60-inch landings. No other condition triggers handrails. Which conclusion is correct?
Show answer & explanation
Correct answer: A - The omission is acceptable; with no other trigger, a 5.5-inch rise does not require ramp handrails
Domain 2: Site Construction
Question 3
A field density test reports 126 pcf wet density at 10% moisture content. The applicable Proctor test gives a maximum dry density of 120 pcf, and the specification requires at least 95% relative compaction. Rounding the final percentage to the nearest 0.1%, which result is correct?
Show answer & explanation
Correct answer: D - 95.5%; passes, after converting wet density to dry density
Domain 3: Concrete
Question 4
Fresh structural concrete containing highly porous lightweight aggregate is specified at 5% to 7% air. A technician uses a pressure air meter and reports 5.8%. Before accepting the concrete on the basis of that reading, how should the result be handled?
Show answer & explanation
Correct answer: D - Set aside the pressure-meter result and verify air content with a volumetric method suitable for highly porous aggregate concrete
Domain 4: Masonry
Question 5
After wind-driven rain, water appears at both jambs below a brick-veneer window. Through-wall flashing is present above the lintel, and the center weeps are open, but the flashing terminates flat at each jamb without turned-up ends. The missing detail is:
Show answer & explanation
Correct answer: C - Provide turned-up end dams at both jambs and integrate them continuously with the through-wall flashing
Domain 5: Metals
Question 6
During steel erection, two open-web steel joists have been set, but the specified bridging has not been installed. The crew proposes placing bundles of metal deck on the joists to save crane time. The superintendent's instruction should be:
Show answer & explanation
Correct answer: D - Install the specified bridging and required stability restraints before any construction load is placed
Domain 6: Wood
Question 7
An HVAC installer cuts one web member of a metal-plate-connected roof truss to clear a duct. Adjacent trusses remain undamaged, and the temporary erection bracing is intact. The best immediate response is:
Show answer & explanation
Correct answer: B - Restrict loading in the affected area, shore the damaged truss as needed, and obtain a written repair detail from the truss designer
Domain 8: Doors, Windows, and Glazing
Question 8
A fixed annealed-glass pane beside an interior corridor has an exposed area of 12 square feet. Its bottom edge is 12 inches above the floor, its top edge is 72 inches above the floor, and the walking surface is 18 inches from the glass. No guard, barrier, or code exception applies. Which corrective action is required?
Show answer & explanation
Correct answer: B - Replace it with listed safety glazing, such as fully tempered or qualifying laminated glass
Domain 12: Procurement and Contracting Requirements
Question 9
On a renovation project, the owner's field representative orally directs the superintendent to move a rated wall 2 feet. The contract states that only the owner's contracting officer may authorize changes. The relocation is not needed for safety and does not block unrelated work. The contractor should:
Show answer & explanation
Correct answer: A - Document the directive, hold the relocation, give required notice, obtain authorized direction, and continue unaffected work
Question 10
An estimator calculates a fully loaded project cost of $1,280,000, including direct costs, project indirect costs, and allocated home-office overhead. Management requires a 20% margin on the final selling price. What bid price meets that target before alternates?
Show answer & explanation
Correct answer: B - $1,600,000, which produces a 20% margin on price